Breaking Down and Sizing Work Items

#49 - Visualizing Your Value Stream With Kanban - Dimitar Karaivanov
Topic 3 of 12
Published Aug 2, 2021 · Clip 17:48–20:26 (2:38)
Dimitar discusses how to size work items in Kanban. There's no prescription, but a good practice is making items as small as possible — user stories ideally 1-3 or 4 days, with anything over a week limited to 5-10% of items. At Kanbanize they use T-shirt sizes with expected durations; teams can accept S and M items anytime but should 'push back like hell' on L or XL items, prompting product management to break them down. Most of the time breaking down reveals the smaller piece was what the client actually wanted, so a check against oversized features should be built into the process.