Estimates and Commitments

#103 - Software Development Pearls - Karl Wiegers

Topic 5 of 9

Published Sep 5, 2022 · Clip 31:05–39:45 (8:40)

Karl explains that estimates are best guesses based on knowledge and assumptions, so they should never be given off the top of the head or as point estimates—ranges are better since we can't predict the future precisely. He recounts stories of estimates being treated as commitments and of a project manager bending to pressure, and shares his own story of refusing to commit to an impossible schedule to a senior manager. He advocates under-committing and over-delivering, and notes that refusing unrealistic commitments can lead to negotiation rather than disaster.